It takes 12 painters to paint the walls of a school in 21 days. in how many days the same job will be completed with 14 painters?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 14:30
Your friend swims on the school team. in his first four races, his times are 24.7, 23.5, 25.6, and 27.2 seconds. which time listed for his next race would make the range larger?
Answers: 1
question
Mathematics, 21.06.2019 15:30
On a architect's drawing of a house, 1 inche representa 1.5
Answers: 1
question
Mathematics, 21.06.2019 18:00
What set does not contain -3 the set of all real numbers the set of all integers the set of all whole numbers the set of all rational numbers
Answers: 1
question
Mathematics, 21.06.2019 18:10
The means and mean absolute deviations of the individual times of members on two 4x400-meter relay track teams are shown in the table below. means and mean absolute deviations of individual times of members of 4x400-meter relay track teams team a team b mean 59.32 s 59.1 s mean absolute deviation 1.5 s 245 what percent of team b's mean absolute deviation is the difference in the means? 9% 15% 25% 65%
Answers: 2
You know the right answer?
It takes 12 painters to paint the walls of a school in 21 days. in how many days the same job will b...
Questions
question
Mathematics, 14.04.2021 22:30
question
English, 14.04.2021 22:30
question
Mathematics, 14.04.2021 22:30
question
Chemistry, 14.04.2021 22:30