subject
Mathematics, 18.11.2019 06:31 fendyli6066

The following is a table of activities associated with
a project at rafay ishfaq’s software firm in chicago, their durations,
and what activities each must precede:
activity duration (weeks) precedes
a (start) 1 b, c
b 1 e
c 4 f
e 2 f
f (end) 2 —
a) draw an aon diagram of the project, including activity durations.
b) define the critical path, listing all critical activities in chronological
order.
c) what is the project duration (in weeks)?
d) what is the slack (in weeks) associated with any and all noncritical
paths through the project?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 18:00
If f(x) = 4x – 3 and g(x) = 8x + 2, find each function value a.f[g(3)] b.g[f(5)] c.g{f[g(-4)]}
Answers: 3
question
Mathematics, 21.06.2019 21:10
Given: lines a and b are parallel and line c is a transversal. prove: 2 is supplementary to 8 what is the missing reason in the proof? statement reason 1. a || b, is a transv 1. given 2. ∠6 ≅ ∠2 2. ? 3. m∠6 = m∠2 3. def. of congruent 4. ∠6 is supp. to ∠8 4. def. of linear pair 5. ∠2 is supp. to ∠8 5. congruent supplements theorem corresponding angles theorem alternate interior angles theorem vertical angles theorem alternate exterior angles theorem
Answers: 3
question
Mathematics, 21.06.2019 22:30
My hour hand points between the 8 and the 9 in 35 minutes it will be the next hour. what time is it ?
Answers: 2
question
Mathematics, 21.06.2019 23:00
Joey is asked to name a quadrilateral that is also a rhombus and has 2 pairs of parallel sides.should be his answer
Answers: 1
You know the right answer?
The following is a table of activities associated with
a project at rafay ishfaq’s software fi...
Questions
question
Mathematics, 26.05.2020 20:59
question
Health, 26.05.2020 21:00
question
Medicine, 26.05.2020 21:00
question
Mathematics, 26.05.2020 21:00
Questions on the website: 14481382